Content
# SMCC_Control_Strategy_Rev2 2.docx
> [Open in Google Drive](https://drive.google.com/file/d/1X8ZU2WMcXe1mZWfrg1H41QgLEr1kcax_/view)
This document outlines the unified control strategy for the SMCC recycled water delivery system, detailing PLC implementation for managing water delivery from Laguna County Sanitation District's Waller Park tank to two irrigation ponds at Santa Maria Country Club. It covers the control logic, equipment including booster pumps, Cla-Valves with flow sensors, groundwater wells, and communication between multiple PLCs via a 900 MHz radio network, integrating AutomationDirect and Allen-Bradley platforms using Modbus TCP. The strategy includes modes for prioritizing pond filling, PID valve control, alarm handling, and system communication protocols.